Design and execution of a support for the partial deconstruction of a factory with prefabricated roof based on bracing arches of 38 m free light

Authors

  • I. Serrá

DOI:

https://doi.org/10.3989/ic.2006.v58.i502.385

Keywords:

structural strengthening, deconstruction, roof, arches spanning, structural system

Abstract


This paper presents the design and the execution of a structural strengthening induced by the partial deconstruction of the naves that contain the East bus garage of the Metropolitan Transport of Barcelona. The structure of the roof of the naves consisted of tied precast concrete arches spanning 38 m. The initial state of the structural system of the building and its specific conditions are described to establish the criteria to be considered in the design and execution process of the strengthening. Then, the design and execution of the strengthening needed to guarantee the stability of the roof structure and the main aspects related to the construction process are described. This intervention had a temporary character because the whole building should be deconstructed after a year term. So that, a strengthening that took advantage of the actual capacity of the existing structure was designed. It consisted of adding steel members which, interacting with the existing structure, configured a new structural system against horizontal actions. It was not necessary to strengthen any existing members neither to build new foundation elements.

Downloads

Download data is not yet available.

References

(1) Molins Borrell, C.: Serrà Martín, I., Aspectos fundamentales para el diseño de un refuerzo estructural. Informes de la Construcción, Vol. 55, nº 490 (2004), pp. 39-48.

(2) GEHO-CEB, ATEP, Colegio de Ingenieros de Caminos, Canales y Puertos: ‘’Demolición y reutilización de estructuras de hormigón’’. Recomendaciones y Manuales Técnicos. Estructuras y Edificación E-7. Colegio de Ingenieros de Caminos, Canales y Puertos, Madrid, 1997.

(3) González Barroso, J.M.: ‘’ITEC, Manual de desconstrucció’’. Generalitat de Catalunya, Barcelona, 1995.

(4) Transports Metropolitans de Barcelona: ‘’Proyecto de Depósito y talleres Zona de Levante’’, Barcelona, 1961-1962.

(5) Alegre, V., Roca, P.: ‘’Patología y reparación de edificios de hormigón prefabricado. Evaluación y rehabilitación de edificios’’. Monografía CIMNE, nº 65, Barcelona, 2002.

(6) Marí Bernat, A.R., Molins Borrell, C.: ‘’Estudi de les modificacions a introduir en l’estructura de les cotxeres de llevant de Transports Metropolitans de Barcelona, per a poder-ne realitzar l’enderroc parcial’’. Departamento de Ingeniería de la Construcción, Barcelona, 2001.